As 53 undelivered jetliners sat parked outside Boeing’s Renton, Wash., plant last week, up from just over 40 a month ago, workers inside the factory felt the pressure of constant overtime and an unrelenting buildup of unfinished tasks. Though the company assured Wall Street analysts visiting Seattle that the pileup of Boeing 737 jets has peaked and will be sorted out by year-end, some front-line workers were less optimistic.
Planes awaiting delivery filled the ramps along the edges of Renton Municipal Airport, spilled onto one of the taxiways, and were parked on all available spaces on the Boeing site, along the lakefront and between the buildings.
Of those, 38 were the new 737 MAX model, 14 of them missing their engines. Delays in delivering the MAX model’s new LEAP engines, made by CFM International, are just one of the choke points causing the pileup.
Two workers said the engine supply is noticeably improving. Yet shortages of other parts mean the amount of unfinished work on the jets rolling out in Renton is still growing.
Internal Boeing documents showing detailed operational data viewed by the Seattle Times indicate that on Aug. 30, Boeing Renton was roughly 26,600 jobs behind schedule. A week later, Sept. 6, that total had swelled to about 31,000 jobs behind schedule.
One worker said Boeing has set a daunting target of no more than 50 jobs behind schedule per airplane under assembly by the end of October, which would be a total of about 1,500 jobs.
Those totals include final assembly, wings fabrication
Article source: https://pilotonline.com/business/consumer/article_933aad5a-1f94-50b3-9e25-a290b1410138.html